Asset integrity

When to replace industrial equipment: estimating how long it has left

What a remaining useful life estimate is really worth, the conditions that make it defensible, and the cases where you should refuse to calculate it.

7 min read

Aerial view of a nuclear power plant
Aerial view of a nuclear power plant

Estimating remaining useful life comes down to answering one simple question: on what date will this piece of equipment reach its allowable limit if the observed degradation carries on at the same rate? The formula itself is elementary. The hard part is assembling the conditions that make the result defensible, and knowing how to say when those conditions are not met.

The essentials

A remaining useful life figure is calculated from three inputs: the current measured condition, the allowable limit and the observed rate of degradation. The first comes from the latest inspection campaign, the second from a strength calculation owned by the technical authority or the notified body, and the third from a history of at least three campaigns at the same location. If any one of the three is missing, the figure produced is decorative. An honest tool must then refuse to display it.

What the calculation assumes

Take the most common case, loss of wall thickness through corrosion. The logic runs as follows: you know the current wall thickness at a point, you know the thickness below which the equipment can no longer be kept in service under its operating conditions, and you know the rate at which the gap is closing. The time remaining follows.

Each of these three terms deserves a close look, because each carries its own way of going wrong.

The current wall thickness is the least troublesome, provided it comes from a properly identified location. The whole exercise rests on measuring the same point over time, not a point that merely sits nearby. See tracking the degradation of a piece of equipment on this.

The minimum allowable wall thickness is not a figure you read off an inspection report. It is the result of a calculation that accounts for the service pressure and temperature, the material, the geometry and the rules that apply to the equipment. It belongs to the technical authority, the design office or the notified body. No software can produce it on its own, and any tool that claimed to guess it should be set aside without further discussion. Treating a standard, generic limit as though it applied to your specific vessel is one of the quietest ways to manufacture a reassuring but meaningless number.

The rate of degradation is the most fragile part. It assumes a sufficient history at the same location, under comparable conditions, and above all it assumes that the past informs the future, which is only true as long as the service conditions do not change. The moment the process, the product or the operating regime shifts, the historical rate stops being a guide and becomes a distraction.

The cases where you should refuse to calculate

  • Fewer than three campaigns at the locationtwo values always give you a straight line. The slope obtained can be nothing more than a measurement artefact, and the deadline that flows from it hands out false assurance.
  • Minimum allowable wall thickness unknownwith no limit there is no target, and therefore no life. Displaying a deadline by assuming a standard limit amounts to fabricating information.
  • Change of service conditionsa change of product, temperature or operating regime makes the earlier history unrepresentative. The past rate no longer says anything about the rate to come.
  • Non-uniform degradationlocalised corrosion, pitting or under-deposit attack does not behave like a general loss of thickness. The linear calculation simply does not apply.
  • Points poorly matched between campaignsthis is the most frequent and the most insidious case. The slope is computed across different points and means nothing at all.

In each of these cases, the right answer is not a cautious estimate. It is the absence of an estimate, accompanied by a clear statement of what is missing. A dashboard that displays "insufficient data: two campaigns available" is more useful than one that displays a false date, because it points to the action that needs taking rather than papering over the gap.

On the plant floor

Two vessels, two opposite conclusions

Consider two vessels of the same age, monitored from the same date.

The first has four campaigns at stable condition monitoring locations, showing a steady and moderate loss. The rate is clear, the margin against the allowable limit is comfortable, and the calculated deadline falls well beyond the next revalidation. Conclusion: nothing to do before then, and the inspection interval in place is appropriate.

The second has the same number of campaigns, but the two most recent show a faster loss than the earlier ones, concentrated on three neighbouring locations. The average rate calculated across the whole history would give a reassuring deadline; the recent rate at those three points gives a deadline that is much closer.

It is the second figure that must be escalated. An average taken over the complete history hides exactly the signal you are looking for.

How to present a defensible estimate

A useful estimate is not just a date. It comes with everything needed to judge it. Strip those elements away and you are asking people to trust a number on faith, which is precisely what an audit will not accept.

Element to displayWhy
The condition monitoring location concernedA remaining life applies to a location, not to a whole item of equipment
The number of campaigns usedThree campaigns and eight campaigns do not inspire the same confidence
The period coveredA rate calculated over two years is worth less than a rate over twelve years
The rate used and how it was calculatedAverage rate or recent rate: the choice changes the result
The allowable limit used and its originThis is the figure an auditor will check first
The link to the source reportsWithout traceability, the estimate cannot be defended

Table scrolls horizontally on small screens.

This presentation has a practical advantage: it makes discussion possible. An inspection manager can challenge a chosen rate, ask for a doubtful campaign to be set aside, or flag a change of service. A date shown on its own, without its assumptions, cannot be argued with. It is either endured or ignored, and neither of those is a decision.

What the figure is actually for

A remaining useful life estimate is not meant to trigger a replacement. Its first job is to set the schedule.

It tells you which items of equipment need to be examined at the next turnaround, and which can wait for the one after. It also lets you anticipate an order for a part with a long lead time, or prepare a justification file ahead of a regulatory deadline rather than after it. Aggregated across a fleet, it finally gives management a view of the investment to plan over several years, a very different conversation from the annual scramble for budget.

On that last point, see building the business case for an AI project in maintenance and our Maintenance Intelligence page.

What software does, and what it does not

An asset integrity tool brings three things to the calculation. It automatically matches campaigns by condition monitoring location, so the slope is computed on the same point rather than on a moving target. It applies the same method across the whole fleet rather than to the handful of items that happen to be closely watched. And it keeps the link back to the source reports, so any figure can be traced to the measurement it came from.

What it does not do: decide fitness-for-service, set the minimum allowable wall thickness, or replace the inspector's judgement on the nature of a defect. A serious tool produces an estimate when the data allows it and explicitly flags the cases where the data does not. A figure that cannot be defended in an audit has no practical value, however confident it looks on a screen.

For the overall approach, see asset integrity management. On the equipment families involved, see vessels and tanks and heat exchangers.

Sources and references

API 570, in-service inspection code for piping: derivation of the remaining life from the corrosion rate and the required minimum thickness.

Order of 20 November 2017 on the in-service monitoring of pressure equipment: this is what sets the regulatory deadlines referred to here, independently of any remaining life estimate. Full text on Légifrance

Can you estimate a remaining life with only two campaigns?

You can calculate a slope, but it is not defensible. Two values do not let you tell steady degradation apart from measurement scatter. The honest course is to state that the data is insufficient and to plan an additional campaign.

Who sets the minimum allowable wall thickness?

It belongs to the operator's technical authority, supported as needed by a design office or by the notified body. It depends on the service conditions and the geometry of the equipment. A monitoring tool uses it as an input, it does not produce it.

Should you use the average rate or the recent rate?

Both, shown side by side. The average rate describes long-term behaviour, the recent rate detects accelerations. It is the gap between the two that forms the most useful signal.

Does a remaining useful life figure make the tool liable?

No. It is a decision aid, calculated from supplied data and explicit assumptions. The decision to keep equipment in service, to revalidate it or to replace it remains the operator's, supported where appropriate by an opinion from a notified body.

Written by Adama CamaraAI Consultant · Industry · view profile

Published on March 10, 2026

Support

Custom AI systems for industry

Agents that put your data to work and extend your existing tools. Designed and run on site, off the network.

Visit Assets 4.0